Project Updates for Week of 10/21/2019

10/21/2019

0 Comments

 
​Pavement patching was completed last week along Linden Lane and most of Weber Drive. The contractor anticipates completing water service installations along Carr Street and connecting proposed water mains to the existing water mains at the intersections of Willow Lane and Carr Street and Birch Lane and Carr Street by the end of this week. Pavement patching on Cedar Street and concrete work at various locations throughout the project limits will also occur this week. Residents affected by these activities will receive a notice the day prior to work occurring.
 
Next week, the contractor anticipates connecting the proposed water main to the existing water main within the East Park Apartments northeast parking lot. City and ERA staff are working closely with the East Park Apartments management staff to provide notice to residents affected by this shutdown.
 
By next week, the water main work for this year will be substantially completed in the Phase I area. Pavement and parkway restoration activities will continue in advance of the November 22, 2019 completion date. Additional updates will be provided into November as the work progresses. Remaining water main and service installations in the Phase 2 area along Linden Lane (Oak Lane to Birch Lane), Willow Lane (Linden Lane to Carr Street), and Birch Lane (Linden Lane to Carr Street) will resume next spring. 
0 Comments



Leave a Reply.

    Project Updates

    Check here for updates on the water main project.

    Categories​

    All
    Notice
    Schedule
    Weekly Updates

    RSS Feed

Proudly powered by Weebly
  • HOME
  • ABOUT
    • LOCATION
    • FAQ
  • PROJECT UPDATES
  • CONTACT